Material requirements planning

From Wikipedia, the free encyclopedia

This is an old revision of this page, as edited by 81.178.137.218 (talk) at 23:40, 6 November 2005 (The scope of MRP in manufacturing). The present address (URL) is a permanent link to this revision, which may differ significantly from the current revision.

Material Requirements Planning (MRP) is a software based production planning and inventory control system used to manage manufacturing processes.

An MRP system is intended to simultaneously meet three objectives:

  • Ensure materials and products are available for production and delivery to customers.
  • Maintain the lowest possible level of inventory.
  • Plan manufacturing activities, delivery schedules and purchasing activities.

The scope of MRP in manufacturing


All manufacturing organisations, whatever it is they produce, face the same daily practical problem - Customers want products to be avaialble in a shorter time than it takes to make them. This means that some level of planning is required.

Companies need to control the types and quantities of materials they purchase, plan which products are to be produced and in what quantities and ensure that they are able to meet current and future customer demand, all at the lowest possible cost. Making a bad decision in any of these areas will lose the company money. A few examples are given below:

  • If a company purchases insufficient quantities of an item used in manufacturing, or the wrong item, they may be unable to meet contracts to supply products by the agreed date.
  • If a company purchases excessive quantities of an item, money is being wasted - the excess quantity ties up cash while it remains as stock and may never even be used at all. This is a particularly severe problem for food manufacturers and companies with very short product life cycles.
  • Beginning production of an order at the wrong time can mean customer deadlines being missed.

MRP is used by many organisations as a tool to deal with these problems. The questions it provides answers for are: WHAT items are required, HOW MANY are required and WHEN are they required by. This applies to items that are bought in and to sub-assemblies that go into more complex items.

Inputs and outputs

Running a report from MRP begins with an estimate of what products will be required in the next time period (an arbitrary length of time, often but not always one week), taken from the master production schedule. The MRP software calculates the times required to manufacture the products, using the factory's estimated time to assemble each product. Then, the system explodes the product into lists of parts required, using the bills of materials developed by the engineering department. The parts are ordered at times back-dated (or "offset") from the dates of assembly and the relevant paperwork is generated.

This system works through what are termed inputs and outputs. The inputs are entered into the software, which uses them for processing the outputs. The inputs and outputs essential to an MRP system are as follows:

Inputs

  • Master production schedule. This is a combination of all the known and expected DEMAND for the products being created. The MPS spans a PLANNING HORIZON that includes the present and extends several months, and sometimes even years, into the future. The MPS ONLY addresses the END ITEMS being produced. The component levels will be addressed by the MRP system. This is sometimes referred to as "A production plan for all products". The MPS provides knowledge of DEMAND in these three details:
    1. The END ITEM(s) being created (a.k.a. Independent Demand, Level "O" on BOM)
    2. How much is required at a time
    3. When the quantity(s) are required to meet demand
  • Inventory status records. Records of NET materials AVAILABLE for use already in stock (on hand) and materials on order from suppliers.
  • Bills of materials. Details of the materials, components and subassemblies required to make each product.
  • Planning Data. This includes all the restraints and directions to produce the end items. This includes such items as: Routings, Labor and Machine Standards, Pull/Work Cell and Push commands, Lot sizing technique(s) (i.e. Fixed Lot Size, Lot-For-Lot, Economic Order Quantity), Scrap Percentages, and other inputs.

Outputs

There are only two (2) outputs and a variety of messages/reports

  • Output 1 is the "Recommended Production Schedule" which lays out a detailed schedule of the required minimum start and completion completion dates, with quantities, for each step of the Routing and Bill Of Material required to satisfy the demand from the MPS
  • Output 2 is the "Recommended Purchasing Schedule". This lays out the dates that the purchased items should be both received into the facility AND the date(s) the Purchase Orders, or Blanket Order Release should occur to match the production schedules.

Messages and Reports:

  • Purchase orders. An order to a supplier to provide materials.
  • Reschedule notices. These RECOMMEND cancel, increase, delay or speed up existing orders.

Note that the OUTPUTS are RECOMMENDED. Due to a variety of changing conditions in companys, since the last MRP / ERP system Re-Generation, the recommended outputs need to be reviewed by TRAINED people to group orders for benefits in set-up or freight savings. These actions are beyond the linear calculations of the MRP computer software.

MRP/ERP Systems were first introduced by George Plossl and John Orlicky in the late 1960s. Oliver Wight contributed the evolution to MRP2, to include more than the factory production and material needs. ERP evolved with the change in hardware / software capability and "Interface" interpretations between software.