Uganda Oil Refinery
Country | Uganda |
---|---|
Province | Buseruka Subcounty Hoima District Western Uganda |
City | Kabaale Township |
Coordinates | 01°30′00″N 31°04′48″E / 1.50000°N 31.08000°E |
Refinery details | |
Commissioned | 2027 (Expected)[1] |
Capacity | 30,000 bbl/d (4,800 m3/d) |
The Uganda Oil Refinery is a planned crude oil refinery in Kabaale village, on the Eastern shore of Lake Albert along the Hoima–Kaiso–Tonya Road, Buseruka Sub-county, Hoima District, Western Region, Uganda, near the border with the Democratic Republic of the Congo.[2] It has been planned since 2010. Community opposition was repressed early on. After 5 years of negotiations the Albertine Graben Refinery Consortium (AGRC) formed in 2018 and agreed to design and build the refinery.
The refinery is planned to be fed by the East African Crude Oil Pipeline (EACOP) via a heated northern and a heated southern pipeline, for which the Nzizi Power Station, a 100 megawatt thermal power plant, using natural gas and heavy fuel oil as raw material will be built, a hospital and an international airport.
Location
[edit]The refinery is planned to be built on a 29 square kilometres (11 sq mi) piece of land in Kabaale village, Buseruka Sub-county, Hoima District, Western Region, near the international border with the Democratic Republic of the Congo, on the eastern shore of Lake Albert. The refinery will be located 100 km away from a processing facility, which itself is 100 kilometres (62 mi) north-east of Kingfisher oil field,[3] on the Buhuka Flats at the shores of Lake Albert, in the Kikuube District, connected by a 46 kilometres (29 mi) long feeder pipeline, the southern pipeline.[4] The refinery will also be south of the Tilenga project,[3] which will consist of 6 oil fields and 426 oil wells.[5] The northern pipeline would be 96 kilometres (60 mi) long with a 16-inch diameter and carry oil from Jobi in Nwoya District, Kasemene, Kigogole and other oil fields in Buliisa District, to the refinery.[6] Both pipelines will be electrically heated, since the waxy crude oil from Uganda's oilfields solidifies at room temperature.[6] Thus the refinery will be close to Uganda's largest oil fields in the Kaiso-Tonya area, about 60 kilometres (37 mi), by road, west of Hoima, the location of the district headquarters, and the nearest large city.[7] Kaiso is about 260 kilometres (162 mi), by road, north-west of Kampala, Uganda's capital and largest city.[8]
Overview
[edit]As of 2013, two intake pipelines and one distribution pipeline, with a total construction bill of over US$200 million, were planned to bring crude to the refinery and distribute the finished products to a new terminal in Buloba on the western outskirts of Kampala.[6]
As of 2015 Uganda had proven crude oil reserves of 6.5 billion barrels, about 2.2 billion of which is recoverable.[9] The International Monetary Fund was quoted in 2013 as saying that Ugandas oil reserves are the fourth-largest in sub-Saharan Africa, behind Nigeria, Angola, and South Sudan.[10]
Since some of the largest oil fields are in the Kaiso-Tonya area in Hoima District, the area was selected for Uganda's only oil refinery.[11] The strategy is to build a refinery that meets the petroleum products needs of Uganda and its regional neighbors, with any remaining to be exported.[12][13]
In addition to the refinery, as of 2015 a new airport[14] and a hospital[15] was planned. The Hoima–Kaiso–Tonya Road, which connects Hoima to Kaiso and Tonya along the eastern shores of Lake Albert, passes through Kabaale Village where the refinery will be located.[16] As of 2016 the Nzizi Power Station was planned, a 100 megawatt thermal power plant, using natural gas and heavy fuel oil as raw material.[17]
In 2015, the cost of the refinery was estimated to be US$4.3 billion, with 70 percent of that amount to be borrowed and the remaining 30 percent coming from shareholders.[18] In July 2015, the government hired the Danish Ramboll Group A/S to conduct an "'early phase' detailed route and environmental study for an oil pipeline that will run from the Albertine Graben - Hoima to Buloba...."[19]
History
[edit]As early as 2010, community opposition rose against plans to build the Uganda Oil Refinery, which led to repression against environmental activists.[20]
As of 2011, the government of Uganda had preferred a small production capacity to prolong the longevity of its new oil discoveries.[21] This preference initially pitted it against the three major exploration companies in the country, which preferred rapid harvesting and export of the crude via pipeline to the Kenyan coast.[22]
In March 2013, the government of Uganda engaged the US-based energy investment and consulting firm Taylor Dejongh to carry out an international search for a strategic investor in the refinery.[23]
In October 2013, the government of Uganda invited interested parties to bid for the construction, operation, and 60 percent ownership of the refinery in a public-private partnership arrangement.[24][25]
In January 2014, the Ugandan government shortlisted the following six consortia out of fifteen applicants for possible selection as strategic investor in the refinery: China Petroleum Pipeline Bureau ( People's Republic of China), Marubeni Corporation (Japan), Petrofac (United Arab Emirates), RT Global Resources (Russia), SK Energy (South Korea), and Vitol (the Netherlands).[26]
In June 2014, media reports indicated that four of the six companies had submitted detailed proposals for the construction of the refinery.[27] At that time, the firms still left in the bidding were China Petroleum Pipeline Bureau, Marubeni Corporation, RT Global Resources, and SK Energy.[28][29]
In June 2014, it was reported that consortia led by RT Global Resources and SK Energy had emerged as the two best contenders. They were requested to make a last and final proposal so that the winner could be selected by the end of August 2014.[30]
In February 2015, media reports indicated that the consortium led by RT Global Resources (also including Telconet Capital Limited Partnership, VTB Capital, JSC Tatneft, and the GS Engineering and Construction Corporation) had won the bid to build the refinery.[31][32][33][34][35]
According to a July 2016 report, talks between the government of Uganda and RT Global Resources which had started in February 2015 broke down, and the consortium pulled out.[36] Uganda then began negotiations with the reserve bidder, the consortium led by SK Engineering & Construction of South Korea.[37] The new consortium members included SK Engineering and Construction, the KBD Global Investment Partnership Private Equity Fund, the China State Construction Engineering Corporation, Haldor Topsøe A/S, and Maestro Oil and Gas.[38]
In late 2016, negotiations with the consortium led by SK Engineering & Construction also broke down.[39] Negotiations were then started with a new consortium led by Guangzhou Dongsong Energy Group, a Chinese company. Others in that consortium included (a) China Petroleum Engineering & Construction Corporation (CPECC) (b) China Africa Fund for Industrial Cooperation (CAFIC) (c) Guangzhou Silk Road (d) East China Design and Engineering Institute (e) Exim Bank of China and (f) Industrial and Commercial Bank of China (ICBC). Those talks collapsed in June 2017 when CPECC, the main contractor in the consortium, pulled out of the talks.[40]
In August 2017, a new consortium led by General Electric of the United States and Jk Minerals Africa of South Africa agreed to build the US$4 Billion refinery and to own 50 and 10 percent respectively, while the government of Uganda and other investors would take up the remaining 40 percent. Other members in this new consortium were (i) Yaatra Ventures LLC, (ii) Intracontinent Asset Holdings and (iii) Saipem SpA of Italy.[41] These firms were competitors during the initial bidding, but they came together and formed a special purpose vehicle, the Albertine Graben Refinery Consortium (AGRC), to design, procure the necessary supplies and build the refinery.[39][42][43]
Ownership
[edit]In 2015, General Electric was expected to take up 50 percent and Jk Minerals Africa 10 percent. The government of Uganda proposed that the remaining 40 percent be divided among itself, Burundi, Kenya, Rwanda, and Tanzania in equal shares,[18] except that Uganda would assume whatever ownership interests are not subscribed by the other countries.[18][44] Kenya agreed to purchase a 2.5 percent interest in the refinery for an estimated KES:5.6 billion.[45][46] As of 2016, it had not decided whether to increase that interest to the maximum of 8 percent, saying that it needed to further evaluate the project's commercial value in light of the government's budgetary constraints.[18]
In 2014 Burundi and Rwanda submitted letters of interest to Uganda.[47] Burundi did not decide the extent of its ownership interest, waiting on the feasibility study of the refinery and a detailed statement of anticipated costs.[47]
In 2016, Tanzania committed to pay US$150.4 million for 8 percent ownership in the refinery.[48][49]
In October 2016, it was reported that TotalEnergies of France had committed to acquiring 10 percent shareholding in the refinery.[50][51]
As of April 2018 the tentative ownership table was as follows:[52]
Rank | Name of Owner | Percentage Ownership |
---|---|---|
1 | General Electric of the United States | 50.0
|
2 | Uganda Refinery Holding Company | 19.5
|
3 | JK Minerals Africa[53] | 10.0
|
4 | TotalEnergies of France[54] | 10.0
|
5 | Tanzania Petroleum Development Corporation | 8.0
|
6 | National Oil Corporation of Kenya | 2.5
|
7 | Other Investors | |
Total | 100.00
|
Agreement
[edit]In April 2018, the Albertine Graben Refinery Consortium signed a definitive agreement with the government of Uganda, committing to design, develop, finance, construct, operate and maintain the planned 60,000-barrel-per-day Uganda Oil Refinery in Hoima District, in the Western Region of Uganda[55] The signing of this Project Framework Agreement, allows for the commencement of the Front End Engineering and Design, Project Capital and Investment Costs Estimation (PCE) and environmental impact assessment and social impact assessments.[56]
In August 2018, the Albertine Graben Refinery Consortium (AGRC), selected Saipem SpA of Italy and a member of AGRC to begin with the FEED study, at a contract price of US$68 million. The study is expected to last 17 months, to be followed by the engineering, procurement, and construction phase.[57][58]
In March 2022, following meetings with AGRC principals in Italy, Ruth Nankabirwa, the Ugandan oil minister at that time, estimated that FID for the refinery might be reached in 2023 and commercial operations could be expected in 2027.[1]
On 30 June 2023, the deadline for AGRC to reach financial close expired without funding acquisition. The government of Uganda, which had extended the deadline twice before, declined to do it a third time. According to media reports, Uganda is considering working with Sonatrach Petroleum Corporation of Algeria and with the member states of the East African Community in order to raise the necessary funding and the technical expertise to build the refinery and bring it online by 2027.[59][60]
Developments
[edit]In January 2024, it was disclosed that the government of Uganda had entered into negotiations with Alpha MBM Investments LLC, based in Dubai, whose shareholders include members of the Dubai Royal Family, to explore the possibility of the Middle Eastern investors funding the refinery. Negotiations are expected to conclude during Q2 of 2024.[61][62][63]
In November 2024, online media quoting Ruth Nankabirwa, Uganda's oil minister, reported that the Ugandan government and their Dubai-based partners Alpha MBM Investments, have decided to "wholly finance the $4-billion oil refinery project through equity".[64] Alpha MBM Investments have assured that they have adequate funds to fund their equity participation in the project.[65]
The refinery project also involves the construction of a multi-products pipeline from Kabaale in Hoima District to Namwabula in Mpigi District measuring 211 kilometres (131 mi), a refined product storage terminal in Namwabula and a raw water intake pipe from Lake Albert to the refinery in Kabaale.[66]
In addition to premium motor spirit, the refinery is expected to produce jet fuel, diesel fuel, kerosine, liquefied petroleum gas (LPG) and other products of crude oil distillation. An estimated total of 100,000 kilograms (220,462 lb) of LPG are expected to be generated at the refinery (20 percent from Kingfisher) and (80 percent from Tilenga), on an annual basis.[67]
See also
[edit]- Hoima–Kampala Petroleum Products Pipeline
- Petroleum Authority of Uganda
- Kenya–Uganda–Rwanda Petroleum Products Pipeline
- Uganda National Oil Company
- Uganda–Kenya Crude Oil Pipeline
References
[edit]- ^ a b Paul Murungi (21 March 2022). "Oil refinery to start operations in 2027 - govt". Daily Monitor. Kampala, Uganda. Retrieved 22 March 2022.
- ^ Paul Richardson, and Fred Ojambo (30 September 2014). "Uganda Mulls $1 Billion Eurobond Sale to Fund Infrastructure". Bloomberg News. Retrieved 17 February 2015.
- ^ a b Patience Atuhaire (9 February 2022). "Why Uganda is investing in oil despite pressures to go green". BBC News. Retrieved 8 March 2023.
- ^ "Kingfisher Oil Field Development, Lake Albert Rift Basin, Uganda". 2020. Retrieved 8 March 2023.
- ^ "McDermott wins EPCC contract for Tilenga project, Uganda". Oil Review Africa Online. 11 June 2021. Retrieved 8 March 2023.
- ^ a b c ORA (27 May 2013). "Uganda to build petroleum distribution terminal and two new pipelines". Oil Review Africa (ORA). Retrieved 2 January 2015.
- ^ "Road Distance Between Hoima, Uganda And Kaiso, Uganda" (Map). Google Maps. Retrieved 23 April 2021.
- ^ "Road Distance Between Kampala, Uganda And Kaiso, Uganda" (Map). Google Maps. Retrieved 23 April 2021.
- ^ Patey, Luke (October 2015). "Oil in Uganda: Hard bargaining and complex politics in East Africa" (PDF). Oxford: Oxford Institute for Energy Studies. Retrieved 28 April 2016.
- ^ Fred Ojambo and, Nidaa Bakhsh (8 October 2013). "Uganda Seeks Investor to Build $2.5 Billion Oil Refinery". Bloomberg News. Retrieved 9 May 2014.
- ^ Ladu, Ismail Musa (18 September 2012). "Uganda confirms more oil deposits". Daily Monitor. Kmpala. Retrieved 9 May 2014.
- ^ Ouga, Samuel (14 August 2013). "Uganda's Oil Refinery – An Opportunity for transformation". New Vision. Kampala. Retrieved 9 May 2014.
- ^ DSTC (13 June 2012). "Hoima Refinery Threatened By Kenyan Discoveries". Downstreamtoday.com (DSTC). Retrieved 8 March 2015.
- ^ Kazibwe, Kenneth (11 June 2015). "OIL: Government to Construct Airport in Hoima, Pipeline". Kampala: Chimpreports.com. Retrieved 19 February 2016.
- ^ Robert Atuhairwe, Benedict Okethwengu (15 November 2014). "Refinery land: Sh30b compensation paid". New Vision. Kampala. Retrieved 2 February 2016.
- ^ Vision Reporter (11 August 2011). "Hoima-Kaiso Tonya Road Works Start". New Vision. Kampala. Archived from the original on 16 August 2011. Retrieved 30 August 2014.
- ^ OIUM (2 July 2013). "Gas: not the main meal but a useful side dish". Kapala: Oil In Uganda Magazine (OIUM). Retrieved 2 February 2016.
- ^ a b c d Makene, Prosper (4 June 2015). "Government to speak on eight percent share purchase in Ugandan oil refinery when the time is ripe". Dar es Salaam: IPP Media. Retrieved 2 February 2016.
- ^ Musisi, Frederic (17 July 2015). "Government hires Danish firm to study oil pipeline route". Daily Monitor. Kampala. Retrieved 2 February 2016.
- ^ Lakhani, Nina; reporter, Nina Lakhani climate justice (19 October 2023). "'Very disturbing': crackdown on oil pipeline protests in Uganda concerns UN rights expert". The Guardian. ISSN 0261-3077. Retrieved 9 December 2023.
- ^ Nakazzi, Esther (14 June 2011). "Shs14.7 billion allocated towards in-country refinery". Daily Monitor. Kampala. Retrieved 2 January 2015.
- ^ Staff Writers (18 April 2013). "Uganda wanes off foreign pressures as oil production nears". Daily Monitor. Kampala. Retrieved 9 May 2014.
- ^ Ssekika, Edward (1 March 2013). "Govt hires transaction advisor for oil refinery". The Observer (Uganda). Kampala. Retrieved 2 February 2016.
- ^ Kasita, Ibrahim (9 October 2013). "Uganda invites interested firms to build oil refinery". New Vision. Kampala. Retrieved 9 May 2014.
- ^ Musoke, Ronald (17 December 2013). "Uganda shortlists six firms to build oil refinery". The Independent (Uganda). Kampala. Retrieved 2 January 2015.
- ^ Abdallah, Halima (28 December 2013). "Uganda Shortlists 6 Companies for The Oil Refinery Tender". The EastAfrican. Nairobi. Retrieved 9 May 2013.
- ^ Administrator (9 June 2014). "Uganda Moves Closer to Building $2.5bn Oil Refinery". Kampala: Chimprepors.com (CRC). Retrieved 2 February 2016.
- ^ Musisi, Frederic (5 June 2014). "Refinery tender enters third phase, four firms submit bids". Daily Monitor. Kampala. Retrieved 5 June 2014.
- ^ Odyek, John (5 June 2014). "Four companies submit proposals for development of Uganda's oil refinery". New Vision. Kampala. Retrieved 5 June 2014.
- ^ Odyek, John (25 June 2014). "Govt selects two final bidders for oil refinery". New Vision. Kampala. Retrieved 25 June 2014.
- ^ Mbanga, Jeff (12 May 2015). "From Russia with refining capacity". Kampala: Theafricareport.com (TARC). Retrieved 2 February 2016.
- ^ Biryabarema, Elias (17 February 2015). "UPDATE 2-Uganda picks Russia's RT Global Resources to build refinery". London: Reuters. Archived from the original on 24 December 2015. Retrieved 17 February 2015.
- ^ Odhiambo, Allan (18 February 2015). "Uganda picks Russian firm for oil refinery". Business Daily Africa. Nairobi. Retrieved 18 February 2015.
- ^ Ssekika, Edward (18 February 2015). "Why gov't picked Russian firm for oil refinery". The Observer (Uganda). Retrieved 18 February 2015.
- ^ Mugerwa, Francis (12 July 2015). "Oil refinery construction to begin before December". Daily Monitor. Kampala. Retrieved 12 July 2015.
- ^ Musisi, Frederic (1 July 2016). "Russian firm pulls out of Uganda's $4 billion oil refinery". The EastAfrican. Nairobi. Retrieved 1 July 2016.
- ^ Biryabarema, Elias (1 July 2016). "Uganda switches bidder in talks over long-delayed $2.5 billion refinery". Reuters.com. Archived from the original on 2 July 2016. Retrieved 1 July 2016.
- ^ Abdallah, Halima (2 July 2016). "Uganda begins fresh negotiations for oil refinery". The EastAfrican. Nairobi. Retrieved 2 July 2016.
- ^ a b Biryabarema, Elias (7 August 2017). "Uganda says agrees terms with consortium to build oil refinery". Reuters.com. Retrieved 13 August 2017.
- ^ Matsiko, Haggai (31 July 2017). "Uganda: Chinese Quit Museveni's Refinery Deal". The Independent (Uganda) via AllAfrica.com. Kampala. Retrieved 7 August 2017.
- ^ Abdallah, Halima (21 August 2017). "How Chinese firm DongSong lost lucrative refinery deal". The EastAfrican. Nairobi. Retrieved 21 August 2017.
- ^ Frederic Musisi, and Jonathan Adengo (7 August 2017). "Italian, USA firms win refinery deal". Daily Monitor. Kampala. Retrieved 7 August 2017.
- ^ Presidential Press Unit (23 October 2017). "President Museveni, General Electric group discuss oil refinery". Entebbe: Uganda State House. Retrieved 26 January 2018.
- ^ "Bulk of Uganda commercial oil production to start in 2017-minister". Reuters. Thomson Reuters. 9 May 2014. Archived from the original on 12 May 2014. Retrieved 18 July 2015.
- ^ Odhiambo, Allan (19 January 2015). "Kenya Acquires Sh5.6 Billion Stake in Uganda Refinery". Business Daily Africa. Nairobi. Retrieved 18 July 2015.
- ^ Anyanzwa, James (21 March 2015). "Kenya to pay $13 million for Uganda refinery stake". The EastAfrican. Nairobi. Retrieved 21 March 2015.
- ^ a b Abdallah, Halima (19 July 2014). "Neighbours sign up for Uganda refinery shares". The EastAfrican. Retrieved 19 July 2014.
- ^ Kasumuni, Ludger (30 April 2016). "TZ to spend Sh300bn buying stake in Uganda refinery". The Citizen (Tanzania). Dar es Salaam. Retrieved 14 July 2016.
- ^ Senelwa, Kennedy (30 July 2016). "Tanzania secures 8pc stake in Uganda's $2.5b oil refinery". The EastAfrican. Nairobi. Retrieved 1 August 2016.
- ^ Anyanzwa, James (8 October 2016). "Uganda oil refinery completion date pushed to 2020". The EastAfrican. Nairobi. Retrieved 8 October 2016.
- ^ Joseph Burite, and Fred Ojambo (28 October 2016). "Uganda Says Total Will Take Stake in Planned Oil Refinery". Bloomberg News. Retrieved 13 August 2017.
- ^ Musisi, Frederick (12 April 2018). "Investors to fund oil refinery venture". Daily Monitor. Kampala. Retrieved 12 April 2018.
- ^ Mangula, George (22 March 2018). "Oil and gas: MPs take on companies to produce reports". Kampala: Eagle Uganda. Retrieved 18 March 2019.
- ^ UBNC (28 October 2016). "Total to acquire 10% stake in Uganda refinery". Ugbusiness.com (UBNC). Kampala. Retrieved 27 February 2019.
- ^ Biryabarema, Elias (10 April 2018). "Uganda signs agreement with investors to build oil refinery". Reuters.com. Retrieved 10 April 2018.
- ^ The Independent (10 April 2018). "Albertine Graben Consortium signs oil refinery pact with Uganda". The Independent (Uganda). Kampala, Uganda. Retrieved 10 April 2018.
- ^ Brelsford, Robert (3 August 2018). "Consortium Lets FEED Contract for Uganda's First Refinery". Houston: Oil & Gas Journal. Retrieved 9 August 2018.
- ^ Frederic Musisi (9 August 2018). "Italian Firm Given Nod On Refinery Design Tender". Daily Monitor. Kampala, Uganda. Retrieved 10 August 2018.
- ^ Elias Biryabarema (4 July 2023). "Uganda seeks new funding for oil refinery after consortium deal lapses". Reuters.com. Retrieved 4 July 2023.
- ^ Julius Barigaba (3 July 2023). "Uganda walks away from US firm-led consortium after refinery contract expires". The EastAfrican. Nairobi, Kenya. Retrieved 4 July 2023.
- ^ "Uganda in talks with UAE investment firm over planned $4 billion oil refinery" (The EastAfrican Quoting Reuters). The EastAfrican. Nairobi, Kenya. 23 January 2024. Retrieved 24 January 2024.
- ^ Julius Barigaba (28 January 2024). "Why Uganda picked UAE firm to refuel its oil refinery project". The EastAfrican. Nairobi, Kenya. Retrieved 28 January 2024.
- ^ Uganda Radio Network (24 January 2024). "Emirati prince enters oil refinery negotiations with Uganda". The Observer (Uganda). Kampala, Uganda. Retrieved 30 January 2024.
- ^ Charles Kennedy (29 November 2024). "Uganda to Fund $4-Billion Oil Refinery after Ditching Efforts to Tap Markets". Oilprice.com. London, England, United Kingdom. Retrieved 30 November 2024.
- ^ Giles Muhame (21 August 2024). "Oil Refinery: To Avoid 'Dangote Scenario', Uganda, UAE Consortium Focus on Crude Oil Supply Agreement". ChimpReports. Kampala, Uganda. Retrieved 30 November 2024.
- ^ Emmanuel Okello (21 November 2024). "Gov't Holding Key Negotiations for Signing of Final Investment Decision for Refinery". Uganda Radio Network. Kampala, Uganda. Retrieved 30 November 2024.
- ^ Wilson Asiimwe (27 December 2023). "Uganda To Produce 100,000 Kg Of Liquified Petroleum Gas Annually". New Vision. Kampala, Uganda. Retrieved 30 November 2024.
External links
[edit]- How Uganda refinery will impact the region As at 16 April 2019.
- Uganda Sets Up Region's First Oil Laboratory
- The Uganda refinery: Satisfying region's demand for petroleum As of 17 October 2018.